Assignments - Survey - Drainage Consultant
Client - Ontario County
Ontario County commissioned Larsen Engineers to conduct a complete assessment of storm water runoff from the community college campus, the Performing Arts Center and their surrounding areas. Larsen Engineers was to correlate this storm water runoff information with possible causes of the concerns voiced previously by the public and propose solutions to the actual flooding and erosion problems. Using the latest available mapping, the Fall Brook watershed, as well as a portion of the watershed that drains FLCC and FLPAC into DEC wetland CL13, was examined. Stream flow monitoring gauges were installed at critical locations. All drainage structures throughout the watershed were inventoried and evaluated. Subsurface conditions in key locations were also examined to determine its role in the conveyance of storm water through the area. |